For solar professionals · free, no signup
Enter the system size, yield and install date. You'll see the LGCs and the annual revenue on the capacity above the STC line: 100 kW before 1 October 2026, 1 MW from 1 October 2026.
Defaults: a 1.5 MW system at a typical NSW yield, installed today. The figures update as you type.
The maths
Annual revenue = the capacity above the STC line × specific yield ÷ 1,000 × the LGC price. It pays out yearly, not upfront, until the scheme ends in 2030. The Mid-scale Solar Regulations put the line at 1 MW from 1 October 2026.
Each term in the figure above.
Not on the same capacity.
Questions
For solar installed from 1 October 2026, the first 1 MW of site capacity earns upfront STCs on a fixed five year deeming period (Mid-scale Solar Regulations, registered 17 September 2026). Only the balance above 1 MW earns LGCs, as a registered power station under the Large-scale Renewable Energy Target. Before 1 October 2026 the line is 100 kW.
One LGC per megawatt-hour generated, checked against meter data each year until the scheme ends in 2030.
LGC prices move with the certificate market. The calculator shows the price it uses and the date of that price beside the figure. Change it under More options to match your quote or broker.
Yes, but not on the same capacity. From 1 October 2026 the first 1 MW takes upfront STCs and the balance earns LGCs each year. Before that date the split is at 100 kW. Amperage models the crossover when sizing.